The deadlines noted below will be used by ICC-ES staff in preparing acceptance criteria for upcoming meetings. For staff to meet these deadlines, and to ensure that items have received adequate technical development and review, proponents of acceptance criteria must themselves meet certain deadlines. The deadline for a proponent to provide ICC-ES staff with a final written proposal, and applicable supporting data, is nine weeks prior to the date the criteria is posted for public review.

October 9, 2018
The Westin Birmingham, Birmingham, AL

PROCESSING OF ACCEPTANCE CRITERIA
June 15, 2018
Criteria proposals must be forwarded to staff. Unless the proposal is going to the hearing simply for committee and industry input, the proposal, by this time, must be substantially final and ready for committee consideration, or it will not be placed on the committee agenda
July 13, 2018
ICC-ES staff begins internal review of draft criteria
August 21, 2018
Staff posts criteria on web site for public review E-blast notice of committee meeting sent to public
September 11, 2018
Public comments due to ICC-ES
September 14, 2018
Public comments posted on web site
September 20, 2018
Rebuttal comments, from proponent only, due to ICC-ES
September 25, 2018
Rebuttal comments posted on website
October 01, 2018
Visual presentations due to ICC-ES
October 05, 2018
Memos to Evaluation Committee posted on web site
[back to top]

February 5 – 6, 2019
Hilton Los Angeles Airport, Los Angeles, CA

PROCESSING OF ACCEPTANCE CRITERIA
October 17, 2018
Criteria proposals must be forwarded to staff. Unless the proposal is going to the hearing simply for committee and industry input, the proposal, by this time, must be substantially final and ready for committee consideration, or it will not be placed on the committee agenda
November 07, 2018
ICC-ES staff begins internal review of draft criteria
December 20, 2018
Staff posts criteria on web site for public review E-blast notice of committee meeting sent to public
January 10, 2019
Public comments due to ICC-ES
January 14, 2019
Public comments posted on web site
January 21, 2019
Rebuttal comments, from proponent only, due to ICC-ES Visual presentations due to ICC-ES
January 24, 2019
Rebuttal comments posted on website
February 02, 2019
Memos to Evaluation Committee posted on web site
[back to top]

June 4 – 5, 2019
Hilton Los Angeles Airport, Los Angeles, CA

PROCESSING OF ACCEPTANCE CRITERIA
February 22, 2019
Criteria proposals must be forwarded to staff. Unless the proposal is going to the hearing simply for committee and industry input, the proposal, by this time, must be substantially final and ready for committee consideration, or it will not be placed on the committee agenda
March 15, 2019
ICC-ES staff begins internal review of draft criteria
April 19, 2019
Staff posts criteria on web site for public review E-blast notice of committee meeting sent to public
May 10, 2019
Public comments due to ICC-ES
May 14, 2019
Public comments posted on web site
May 20, 2019
Rebuttal comments, from proponent only, due to ICC-ES Visual presentations due to ICC-ES
May 23, 2019
Rebuttal comments posted on website
May 31, 2019
Memos to Evaluation Committee posted on web site
[back to top]

October 8 – 9, 2019
The Westin Birmingham, Birmingham, AL

PROCESSING OF ACCEPTANCE CRITERIA
June 14, 2019
Criteria proposals must be forwarded to staff. Unless the proposal is going to the hearing simply for committee and industry input, the proposal, by this time, must be substantially final and ready for committee consideration, or it will not be placed on the committee agenda
July 12, 2019
ICC-ES staff begins internal review of draft criteria
June 20, 2019
Staff posts criteria on web site for public review E-blast notice of committee meeting sent to public
September 10, 2019
Public comments due to ICC-ES
September 13, 2019
Public comments posted on web site
September 19, 2019
Rebuttal comments, from proponent only, due to ICC-ES Visual presentations due to ICC-ES
September 24, 2019
Rebuttal comments posted on website
October 04, 2019
Memos to Evaluation Committee posted on web site
[back to top]